BALOCHISTAN-PACKAGE-1 Map

BALOCHISTAN-PACKAGE-1

INTRODUCTION

 

This package deals with the provision of Optic Fibre Connectivity to Dasht, Noshki, Dalbandin, Mashkhel and Taftan Tehsil HQs including Dringar, Ahmadwal, Nokundi and Chaghi cities of Balochistan Province. A population of around 335 thousand people residing in 9 Tehsils and towns will benefit from this project with 887 kilometers of Optic Fibre Cable.

 

Auction Detail:

Package ID:
 
USF/SP/Fibre Optic/2009/Baluchistan-Package 1
 
Advertised On:
 
6th February 2009
 
Bidders Registered:
 
1.     Link Direct International Pvt. Ltd.
2.     Multinet Pakistan (Pvt.) Ltd.
3.     Pakistan Telecommunication Company Limited (PTCL)
4.     Wateen Telecom Pvt. Ltd.
 
Opening of Qualification & Services Proposals:
 
Following registered bidders submitted their Qualification & Services Proposals on 30th March 2009;
 
1.     Multinet Pakistan (Pvt.) Ltd.
2.     Pakistan Telecommunication Company Limited (PTCL)
3.     Wateen Telecom Pvt. Ltd.
 
Financial Bid Opening of Technically Qualified Bidders:
 
Following bidders were declared Technically Qualified and their Financial Bids were opened on 23rd April 2009. Subsidy requested by each bidder is as follows;
 
         1.   PTCL                          Pak Rs. 568,000,000 /-
         2.  Wateen                      Pak Rs. 374,000,000 /-
 
Result:
 
M/s Wateen Telecom Pvt. Ltd. was declared as the lowest qualified bidder and contract, worth Pak Rs. 374,000,000 /-, was signed with Wateen on 17th May 2009.

 

Current Status:

 
Tehsil+Towns 
Length of Optic Fibre (in kms)
Operator
Contracted
Connected
Audited
Contracted
Laid
Audited
Wateen 
9
9
894.7
894.7
894.7

Technical Audit:

 For details regarding selection of Technical Auditor click here

Technical Audit Offer Date     Audit Start Date Audit Completion Date
TA of Milestone 1 (25% work) 02-Mar-2010 22-Mar-2010 29-Mar-2010
TA of Milestone 2 (50% work) 21-Feb-2012 21-May-2012 29-Jun-2012
TA of Milestone 3 (75% work) 21-Feb-2012  21-May-2012 29-Jun-2012
TA of Milestone 4 (100% work) 04-May-2012  21-May-2012 29-Jun-2012
Information Package

Information of Balochistan Package-1 can be downloaded from here.

For WinZip Format click here. 

For WinRaR Format Click here

(If you don't have WinZip, please download from here)
(If you don't have WinRaR, please download from here)