BALOCHISTAN-PACKAGE-2 Map

BALOCHISTAN-PACKAGE-2

INTRODUCTION

 

The Balochistan-Package 2 has been launched for bidding to provide Optic Fibre Connectivity to Bela, Pasni, Turbat and Hub Tehsil HQa including Jhal Jao, Awaran, Dureiji, Peerdrk, Dasht, Mehnaz, Buleda, Kalag,Jiwani, Kalatuk, Nodaiz, Hoshab, Nasirabad, Bilecha, Tump, Gwadar, Uthal, Duddar, Kanraj cities. The un-served tehsils have a population of 995,277 and it will benefit from this project with 1,396 kms of Optic Fibre Cable.

Auction Detail

Package ID:
USF/SP/FibreOptic/2009/Baluchistan-Package-2
Advertised On:
24th April 2009
Bidders Registered:
  1. Link Direct International Pvt. Ltd.
  2. Pakistan Telecommunication Company Limited (PTCL)
  3. Wateen Telecom Pvt. Ltd.
  4. Worldcall Telecom Ltd.  
Opening of Qualification & Services Proposals:
Following registered bidders submitted their Qualification & Services Proposals on 8th June 2009;
 
1.     Pakistan Telecommunication Company Limited (PTCL)
2.     Wateen Telecom Pvt. Ltd.
3.     Worldcall Telecom Ltd.
 
Financial Bid Opening of Technically Qualified Bidders:
Following bidders were declared Technically Qualified and their Financial Bids were opened on 12th June 2009. Subsidy requested by each bidder is as follows;
 
       1.     PTCL                       Pak Rs. 1,200,000,000/-
       2.    Worldcall                Pak Rs. 3,069,280,000/-
 
Result:
M/s Pakistan Telecommunication Company Limited was declared as the lowest qualified bidder and contract, worth Pak Rs. 1,200,000,000/-, was signed with PTCL on 25th June 2009.

 

Current Status

 
Tehsil+Towns 
Length of Optic Fibre (in kms)
Operator
Contracted
Connected
Audited
Contracted
Laid
Audited
PTCL
13
13
13
1290.982
1290.982
1290.982

Technical Audit
 For details regarding selection of Technical Auditor click here

Technical Audit Offer Date     Audit Start Date Audit Completion Date
TA of Milestone 1 (25% work) 10-May-2010 24-May-2010 27-May-2010
TA of Milestone 2 (50% work) 21-May-2010 28-May-2010  04-Jun-2010
TA of Milestone 3 (75% work) 29-Feb-2012 08-Mar-2012  22-Mar-2012
TA of Milestone 4 (100% work)  30-Jan-2020  13-Feb-2020  21-Feb-2020
Comments:

Work in rest of the milestones is under progress.

Information Package

Information Package can be downloaded from here.

For revised Schedules A and B for Package 2 Click Here.