INTRODUCTION
NG-BSD Chitral Lot aims to provide coverage to Unserved/Underserved mauzas in the districts of Chitral, Upper Dir, Lower Dir. A total of 648 mauzas are to be provided Broadband Internet Services. Out of these, 77 mauzas are unserved with regards to voice telephony services and hence will be provided both Voice as well as Broadband Internet Services, whereas 571 underserved mauzas are being targeted for provision of Broadband Internet Services.
Universal Service Fund and Telenor Pakistan entered in the contract to provide basic telephony and data services to the mass population in un/under-served areas of NG-BSD Chitral Lot on 11th Nov 2021.
Package ID:
|
NG-BSD/LOT15-CHITRAL/2020
|
||||
Advertised On:
|
12th July 2020
|
||||
Bidders Registered:
|
1. CMPak Ltd.
2. Pak Telecom Mobile Limited.
3. Pakistan Mobile Communication Limited.
4. Telenor Pakistan (Pvt) Ltd.
|
||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted the Qualification & Services and Subsidy Proposals on 31st Aug 2020:
1. PMCL.
2. Telenor
|
||||
Financial Bid Opening of Technically Qualified Bidders:
|
PMCL & Telenor were declared Technically Qualified and Financial Bid was opened on 11th September 2020. Subsidy requested is as follows:
|
||||
Result:
|
Telenor was declared as the lowest qualified bidder and contract, worth Pak Rs. 1,372,085,052/-, was signed with Telenor on 11th Nov 2020.
|
Current Status
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% work) |
26-Oct-2021 |
30-Oct-2021 | 20-Nov-2021 |
TA of Milestone 2 (50% work) |
15-Nov-2022 | 19-Nov-2022 | 27-Nov-2022 |
TA of Milestone 3 (75% Work) |
25-Sep-2023 |
04-Oct-2023 | 01-Nov-2023 |
TA of Milestone 4 (100% Work) |
11-Dec-2023 |
16-Dec-2023 |
10-Jan-2024 |
Mauzas
Contracted |
Covered |
Audited |
648 |
486 |
486 |