PROJECTS

KHYBER LOT Map

KHYBER LOT

  • INTRODUCTION

     

     Khyber Lot comprises of unserved areas in Khyber Agency, Kohat, Karak, Hangu, FR Peshawar and FR Kohat. Total Mauza in Khyber Lot are 720 with an approximate rural population of 3.1 million. About 70% of the mauza are un-served that covers 56.6% of rural population of this lot..

    Universal Service Fund and PTML (Ufone) entered in the contract to provide basic telephony and data services to the mass population in un-served areas of Khyber Lot on October 23, 2017.

     

    Auction Details: 

     

    Lot ID: 

    BSD/LOT22A-KHYBER/2017

    Advertised On:

      22nd May 2017

    Bidders Registered:

    1.  Pakistan Mobile Communication Ltd. (PMCL)
    2.  Pak Telecom Mobile Limited (PTML)
    3.  Telenor Pakistan Pvt. Ltd.

    Opening of Qualification & Services Proposals:

     

    Following registered bidders submitted their Qualification & Services and Subsidy Proposals on  28th July 2017;

                       

    1.  Pakistan Mobile Communication Ltd. (PMCL)
    2.  Pak Telecom Mobile Limited (PTML)

    3.  Telenor Pakistan Pvt. Ltd.

    Financial Bid Opening of Technically Qualified Bidders:

     

    All bidders were declared Technically Qualified and Financial Bids were opened on 12th September 2017. Subsidy requested is as follows;

     

    Bidder

    Capex Subsidy (PKR)

    Opex Subsidy (PKR)

    1- PMCL

    3,654,201,018/-

    282,979,407/-

    2- PTML    

    1,844,000,000/-

    141,000,000/-

    3- Telenor

    2,725,554,032/-

    286,417,616/-

     

    Result:

    M/s PTML was declared as the lowest qualified bidder and contract, worth Pak Rs. 1,985,000,000/-, was signed with Pak Telecom Mobile Limited on 23rd October 2017.

    Current Status: 

     

    Project Status:

    Under implementation

    Project Work Progress:

    Targets Acheived 

     

     

     

     

     

    Mauzas:

     

    Contracted

    Covered

    Audited

    503

    428

    428

     Technical Audit:

     

     

    Offer   Date  

    Audit Start Date

    Audit Completion Date

     TA of Milestone 1 (25% work)

     04-Oct-18

     07-Nov-18

     24-Nov-2018

     TA of Milestone 2 (50% work)

     14-Mar-19

     26-Mar-19

     26-Apr-19

     TA of Milestone 3 (75% work)

     28-June-2019

     12-Jul-2019

     30-Jul-2019

      TA of Milestone 4

     06-May-2020

     12-May-2020

     02-June-2020

    Comments: