LOT-1 (NH10 & NH25)
INTRODUCTION:
Lot-1, under Next Generation-BSD programme for National Highways and Motorways, is the first project that will focus on providing coverage along the unserved patches of national highways, NH-10 and NH-25. The project is designed specifically for the commuters and for the first-time national roaming has been made part of services to provide seamless coverage to commuters along USF served areas.
Auction Details:
Lot ID:
|
Lot ID: NG-BSD/NH & MW/Lot-1/2018
|
||||||
Advertised On:
|
24th May 2018
|
||||||
Bidders Registered:
|
1. Pakistan Mobile Communication Ltd. (PMCL)
2. Pak Telecom Mobile Limited (PTML) 3. Telenor Pakistan (Pvt.) Ltd. 4. CM Pak (Pvt.) Ltd.
5. Sharp Communication (Pvt.) Ltd. (Provisionally Registered)
6. Cyber Internet Services (Pvt.) Ltd. (Provisionally Registered)
|
||||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted their Qualification & Services and Subsidy Proposals on 6th August 2018;
1. Pak Telecom Mobile Limited (PTML)
2. Telenor Pakistan Pvt. Ltd.
|
||||||
Financial Bid Opening of Technically Qualified Bidders:
|
All bidders were declared Technically Qualified and Financial Bids were opened on 8thOctober 2018. Subsidy requested is as follows;
|
||||||
Result:
|
M/s Pak Telecom Mobile Limited (Ufone) was declared as the lowest qualified bidder and contract, worth Pak Rs. 759,000,000/-, was signed with PTML Pakistan on 11th December2018.
|
Current Status:
Road Segments
|
||
Contracted
|
Covered
|
Audited
|
701.56
|
701.56
|
701.56 |
Technical Audit
|
Offer Date
|
Audit Start Date
|
Audit Completion Date
|
TA of Milestone 1 (25% work)
|
30-Aug-2019 | 11-Sep-2019 | 18-Sep-2019 |
TA of Milestone 2 (50% work)
|
25-Oct-2019
|
06-Nov-2019 | 12-Nov-2019 |
TA of Milestone 3 (75% work)
|
21-Feb-2020
|
05-March-2020 | 12-March-2020 |
TA of Milestone 4 (100% work)
|
26-Feb-2021
|
10-Mar-2021 | 17-Mar-2021 |