PROJECTS
LOT20-MULTAN
INTRODUCTION
NG-BSD Multan Lot aims to provide coverage to Unserved/Underserved mauzas in the districts of Multan and Khanewal. A total of 170 mauzas are to be provided Broadband Internet Services. Out of these, 18 mauzas are unserved with regards to voice telephony services and hence will be provided both Voice as well as Broadband Internet Services, whereas 152 underserved mauzas are being targeted for provision of Broadband Internet Services.
Universal Service Fund and Pakistan Mobile Communications Ltd. (JAZZ) entered in the contract to provide basic telephony and data services to the mass population in un/under-served areas of NG-BSD Multan Lot on 22nd April 2021.
Package ID:
|
NG-BSD/LOT20-MULTAN/2020
|
||||||
Advertised On:
|
12th July 2020
|
||||||
Bidders Registered:
|
1. CMPak Ltd.
2. Pak Telecom Mobile Limited.
3. Pakistan Mobile Communication Limited.
4. Telenor Pakistan (Pvt) Ltd.
|
||||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted the Qualification & Services and Subsidy Proposals on 15th Dec 2020:
1. Pak Telecom Mobile Limited.
2. Telenor Pakistan (Pvt) Ltd.
3. Pakistan Mobile Communication Limited.
|
||||||
Financial Bid Opening of Technically Qualified Bidders:
|
Following bidders were declared Technically Qualified and Financial Bid was opened on 29th December 2020. Subsidy requested is as follows:
|
||||||
Result:
|
PMCL was declared as the lowest qualified bidder and contract, worth Pak Rupees 154,078,229/- was signed with PMCL on 22nd April 2021.
|
Current Status
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% work) |
22-Oct-2021 | 05-Nov-2021 | 14-Nov-2021 |
TA of Milestone 2 (50% work) |
14-Dec-2021 | 22-Dec-2021 | 26-Dec-2021 |
TA of Milestone 3 (75% Work) |
20-May-2022 | 21-May-2022 | 26-May-2022 |
TA of Milestone 4 (100% Work) |
23-May-2022 |
26-May-2022 |
28-May-2022 |
Mauzas
Contracted |
Covered |
Audited |
164 |
164 |
164 |