PROJECTS
NG-BSD NH&MW LOT8 (M4)
INTRODUCTION
This project aims to provide coverage to M4. The total length of un/underserved road segments is 70.67 Kms and Motorway pass through five districts of Punjab, Hafizabad, Faisalabad, Toba Tek Singh, Khanewal & Multan.
Universal Service Fund and PMCL entered in the contract to provide voice and high-speed broadband internet services to the un/underserved road segments of NG-BSD NH&MW-M4 on 22nd June 2022.
AUCTION DETAILS
Package ID: |
NG-BSD/LOT8-NH&MW-M4/2021 |
||||
Advertised On: |
12th November 2021 |
||||
Bidders Registered: |
1. CM Pak Ltd. 2. Pak Telecom Mobile Limited. 3. Pakistan Mobile Communication Limited. 4. Telenor Pakistan (Pvt) Ltd. |
||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted the Qualification & Services and Subsidy Proposals on 1st March 2022: 1. Pakistan Mobile Communication Limited. 2. Telenor Pakistan (Pvt) Ltd.
|
||||
Financial Bid Opening of Technically Qualified Bidders:
|
Following bidders were declared Technically Qualified and Financial Bid was opened on 8th March 2022. Subsidy requested is as follows:
|
||||
Result: |
PMCL was declared as the lowest qualified bidder and contract, worth Pak Rupees 46,703,075/- was signed with PMCL on 22nd June 2022. |
Current Status:
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% Work) |
10-Nov-2022 | 24-Nov-2022 | 01-Dec-2022 |
TA of Milestone 2 (50% Work) |
10-Nov-2022 | 24-Nov-2022 | 01-Dec-2022 |
TA of Milestone 3 (75% Work) |
02-Feb-2023 | 12-Feb-2023 | 16-Feb-2023 |
TA of Milestone 4 (100% Work) |
07-Feb-2023 | 12-Feb-2023 | 16-Feb-2023 |
Mauzas: |
||
Contracted |
Covered |
Audited |
71 |
71 |
71 |