PROJECTS
KPK- EX FATA PACKAGE 1
INTRODUCTION
In FATA Package-1, 653kms OFC to be laid to connect 24 unconnected tehsil headquarters and major towns enroute. Universal Service Fund and PTCL entered in the contract to connect the unserved Tehsil Headquarters and major towns on June 27, 2018.
Auction Details:
Package ID:
|
USF/SP/OPTICFIBER/2018/FATA-PACKAGE-1
|
||||
Advertised On:
|
9th March 2018
|
||||
Bidders Registered:
|
1. LinkdotNet
2. Pakistan Telecommunication Company Limited (PTCL) 3. Telenor LDI Communication (Pvt) Ltd. 4. Telenor Pakistan (Pvt.) Ltd.
5. Wateen Telecom Limited
6. Wi-Tribe Pakistan Limited
|
||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted their Qualification & Services and Subsidy Proposals on 25th April 2018;
1. Pakistan Telecommunication Company Limited (PTCL)
2. Wi-Tribe Pakistan Limited
|
||||
Financial Bid Opening of Technically Qualified Bidders:
|
Both PTCL and Wi-Tribe were declared Technically Qualified and Financial Bids were opened on 11th May 2018. Subsidy requested is as follows;
|
||||
Result:
|
PTCL was declared as the lowest qualified bidder and contract, worth Pak Rs. 700,000,000/-, was signed with PTCL on 27th June 2018.
|
Current Status:
|
Tehsil+Towns |
Length of Optic Fibre (in kms) |
||||
Operator |
Contracted |
Connected |
Audited |
Contracted |
Laid |
Audited |
PTCL |
23 |
23 |
23 |
656.75 |
656.75 |
656.75 |
Technical Audit:
Offer Date
|
Audit Start Date
|
Audit Completion Date
|
|
TA of Milestone 1 (25% work)
|
07-Feb-2020
|
21-feb-2020
|
25-Feb-2020
|
TA of Milestone 2 (50% work)
|
11-Aug-2020
|
12-Aug-2020
|
15-Aug-2020
|
TA of Milestone 3 (75% work)
|
12-Nov-2020
|
20-Nov-2020
|
25-Nov-2020
|
TA of Milestone 4 (100% work)
|
09-Feb-2021
|
18-Feb-2021
|
22-Feb-2021
|
Information Package
Information Package can be downloaded from here